Lower Village Road Safety & Sidewalk Project


The Lower Village Pedestrian Access & Roadway Safety Project’s goal is to address pedestrian access and roadway safety in the Lower Village. The combination of increased vehicle traffic and increased pedestrian and bicycle activity means the potential for danger conflict is growing. A joint working committee of the Planning Commission, Selectboard and area residents, restarted planning after being put on hold during the pandemic. The Committee worked with Chittenden Regional Planning Commission and the engineering consultant firm Stantec to develop alternative designs to improve safety.

In 2024 the Town received a multi-year grant to support design and construction of the project. The project includes the reconfiguration of the Main Road intersections with East and Bridge Streets, construction of sidewalks along the Main Road generally between Raven Ridge and Beaudry’s Store and the north end of East Street, an enclosed drainage system, and reclaiming and re-paving the Main Road in the project area.

An advisory committee was appointed by the Selectboard in 2025 to assist with public outreach and implementing a successful project.

For more information on this project, please contact Town Administrator Adam Argo townadmin@huntingtonvt.org / 802-434-4779

Lower Village Advisory Committee Members

  • Nancy Mead (Chair)
  • Gretchen Schimelpfenig
  • Joe Segale
  • Duncan Keir
  • Jedediah Randall
  • Troy Liberty
  • Paul Stephens

Grant Summary

VTrans Bicycle and Pedestrian Program grant CA0886 (federal project STP BP24(13)). Figures as of October 28, 2026.

Total project budget
$1,522,000
Spent to date
$92,670
Budget remaining
$1,429,330 (93.9%)
Town share spent to date
$18,534

How the project is funded

SourceShareAmount
Federal funds through VTrans80%$1,217,600.00
Town of Huntington (local match)20%$304,400.00
Total$1,522,000.00

Consultant contracts

Firm and roleContractBilled to dateUsed
Donald L. Hamlin Consulting Engineers, Municipal Project Manager$111,669.00$26,794.86
24%
Stantec Consulting Services, design engineer$159,300.00$65,683.38
41%

Reimbursement requests to VTrans

RequestSubmittedWork periodAmount
#1Oct 16, 2025Aug 2025$828.75
#2Apr 1, 2026Sep 2025 to Jan 2026$8,294.71
#3Jul 1, 2026Feb 2026 to May 2026$36,065.84
#4Oct 28, 2026Jun 2026 to Oct 2026$47,480.96
Total$92,670.26

Lower Village Scoping Documents